Hi,
I have a question regarding call dates & plan dates in the maintenance plans. We have a weekly package due every week and the planners want to see this 8 weeks ahead of time. The call date is calculated based on the Call horizon + Call interval in IP30. Since our package is a weekly package, the call date and plan date are apart a maximum of 7 days (Regardless i put 0 or 100% as call horizon). I have to change the call interval in IP30 to get call date 8 weeks ahead of time. But i do not have access to IP30 and its running as a background job which was already scheduled and the interval is 0 there.
Is there anyway i can get the call date 8 weeks ahead of time for a weekly package without changing IP30 parameters?
Any help appreciated.
Nureya